Front Desk Architects and Planners Forum
Estimating Activity Resources of Activity planning - Printable Version

+- Front Desk Architects and Planners Forum (https://frontdesk.co.in/forum)
+-- Forum: Architecture and Planning (https://frontdesk.co.in/forum/forumdisplay.php?fid=1)
+--- Forum: Town Planning and Urban Design (https://frontdesk.co.in/forum/forumdisplay.php?fid=135)
+---- Forum: Project Planning and Management (https://frontdesk.co.in/forum/forumdisplay.php?fid=145)
+---- Thread: Estimating Activity Resources of Activity planning (/showthread.php?tid=2231)



Estimating Activity Resources of Activity planning - manishthak - 01-05-2017

Estimating Activity Resources of Activity planning

Now you have a list of activities and their relative dependencies. The next process associates activities with the resources required to accomplish the work. This process lists each type and amount, or quantity, of each required resource. Every activity requires resources of some sort. 

Activity resources can include

• People
• Equipment
• Materials and supplies
• Money

Estimate Activity Resources is the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity. The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.