Front Desk Architects and Planners Forum
ADVANCE BUILDING CONSTRUCTION IV Year B ARCH. SESSIONAL EXAMS-98 - Printable Version

+- Front Desk Architects and Planners Forum (https://frontdesk.co.in/forum)
+-- Forum: Architecture and Planning (https://frontdesk.co.in/forum/forumdisplay.php?fid=1)
+--- Forum: Study Resource (https://frontdesk.co.in/forum/forumdisplay.php?fid=114)
+---- Forum: Question Paper (https://frontdesk.co.in/forum/forumdisplay.php?fid=174)
+---- Thread: ADVANCE BUILDING CONSTRUCTION IV Year B ARCH. SESSIONAL EXAMS-98 (/showthread.php?tid=3637)



ADVANCE BUILDING CONSTRUCTION IV Year B ARCH. SESSIONAL EXAMS-98 - fdaforum - 11-11-2023

IV Year B ARCH. SESSIONAL EXAMS-98 
DEPARTMENT OF ARCHITECTURE 
MREC (now MNIT) - JAIPUR-302017

ADVANCE BUILDING CONSTRUCTION

Time - 1 Hr.

MKS -

Q1.  Draw details (any three) at

1. Shoulder of steel trussed portal frame.

2. Edge of a block-board counter top

3. Head of sliding door

4. standard road section of a major arterial road.

Q.2 Write very short notes on.

a. Lift slab construction.

b. friction piles.

Q.3.

A. Cable suspended roofs are basically 

1. Tensile structure

2. Compressive structure

3. Open ended framed structures.

B. Pile foundation is prefered in

1. Black cotton/Expansive soils

2. Reclaimed / Landfill areas.

3. Both of the above.

4. None of the above.

C. In slipform R.C.C. construction, form work i moved.

1. after the completion of work

2. 7 days after the completion of casting

3. 14 days after the casing

4. During the casting

D. A space frame can theoritically

a. span up to 40'

b. span upto 80'

c. span upto 120'

d. unlimited span.

E. The property of plastics which makes them most unsuitable for building purposes.

1. Low thermal conductivity.

2. Good moisture resistance.

3. Good electrical insulation.

4. Low weight to sectional area ratio.