Front Desk Architects and Planners Forum
Quantity Surveying & specification B. Arch III yr 1997 - Printable Version

+- Front Desk Architects and Planners Forum (https://frontdesk.co.in/forum)
+-- Forum: Architecture and Planning (https://frontdesk.co.in/forum/forumdisplay.php?fid=1)
+--- Forum: Study Resource (https://frontdesk.co.in/forum/forumdisplay.php?fid=114)
+---- Forum: Question Paper (https://frontdesk.co.in/forum/forumdisplay.php?fid=174)
+---- Thread: Quantity Surveying & specification B. Arch III yr 1997 (/showthread.php?tid=3648)



Quantity Surveying & specification B. Arch III yr 1997 - Manish Jain - 12-16-2023

B. Arch III year examination 1997
DEPARTMENT OF ARCHITECTURE 
MREC (now MNIT) - JAIPUR-302017

Quantity Surveying & specification

Time: Three hours       Max Marks 100

Q. 1. From the plan, elevation and section of a RCC framed building calculate the following : 

a) Earth work in in foundation of column footing and wall 
b) Brickwork with 1:5 cement sand mortar in foundation and plinth of wall 
c) Mild steel work in RCC including bending, binding and  placing in position  
d) 12 mm plaster in 1: 6 cement sand mortar on walls 

Find out cost as per PWD Schedule of Rate 1992.


2 (a) What are various types of Estimate normally required to be for prepared inn construction Residential building?

(b) In a development authority meeting you are required to drawup a preliminary estimate  of a school building for 500 students in order to access the amount of fund. 

The following particulars collected by you : 

carpet area required fer student  1.20 sq.m. 
with an area  of corridor, verandah, levatories, etc to be 20% 
and for walls 15%  to that of plinth area of the building.

Consider plinth aree rate Rs 1200 per sqm.

Cost of water supply    =  5% of the building cost 
Cost of sanitation  = 6% of the building cost 
Coat of electrification  = 10 % of the building cost 
cost of approach road and boundry wall  = 3% of the building cost 
contingency and work changed establishment shall be 5% and 2.5 %  of the building cost 

Q3 Differentiate between 

a) Quotation and Tender 
b) Ernest money of security money 
c) Revised estimate and special repair estimate
d) contingencies and supervision charge

Q4. Explain 
a) A contractor fails to complete his work in spite of repeated reminders , how will you get the work completed
b) What procedure is adopted for cancellatio of an entry in MB ( measurement book) 
c) under what circumstances can
i) A contract be terminated
ii) Material issued when not provided in agreement
iii) payment be made to labour through contractor