01-01-2015, 08:12 AM
Jaipur Development Authority Compounding By-Laws 1982
Voilation of Building By- Laws (compounding charges and penalties)
1.1 Upper Floors : Same compounding charges will be applicable for unapproved construction on each floor.
1.2 Increase in approved building Height
1.2.1 5% increase : 10% of the base rate
1.2.2 10% increase : 25% of the base rate
1.3 Plinth Height : If the basement height is increased in such a way that the plinth height is more than 1.2 M, the basement is considered as ground floor and so the upper floors.
1.4 Staircase Landing (Covered in setback area): This can be compounded if the setback is 3M or more than 3M and projection is not more than 1.5 M and the clear height of the projection is minimum 2.4M from pavement :
1.4.1 upto 4sqm area : 100% of the base rate for front setback and 25% of the base rate for rear and side setbacks.
1.4.2 4sqm to upto 6sqm area : 200% of the base rate for front setback and 50% of the base rate for rear and side setbacks.
1.5 Construction of Flats
1.5.1 Violation of the approved areas of each unit
1.5.1.1 10% area violation : 25% of the base rate for the violated area.
1.5.1.2 More than 10% but upto 20% area violation : 50% of the base rate for the violated area above 10%.
1.6 Projections :
1.6.1 Extra projected distance of chajja :
1.6.1.1 25 % of the approved distance : 25% of the base rate
1.6.1.2 More than 25 % and upto 50% of the approved distance : 50% of the base rate
1.6.2 Extra Projected Distance for floor
Upto 33% of the approved distance : 50 % of the base rate
Voilation of Building By- Laws (compounding charges and penalties)
1.1 Upper Floors : Same compounding charges will be applicable for unapproved construction on each floor.
1.2 Increase in approved building Height
1.2.1 5% increase : 10% of the base rate
1.2.2 10% increase : 25% of the base rate
1.3 Plinth Height : If the basement height is increased in such a way that the plinth height is more than 1.2 M, the basement is considered as ground floor and so the upper floors.
1.4 Staircase Landing (Covered in setback area): This can be compounded if the setback is 3M or more than 3M and projection is not more than 1.5 M and the clear height of the projection is minimum 2.4M from pavement :
1.4.1 upto 4sqm area : 100% of the base rate for front setback and 25% of the base rate for rear and side setbacks.
1.4.2 4sqm to upto 6sqm area : 200% of the base rate for front setback and 50% of the base rate for rear and side setbacks.
1.5 Construction of Flats
1.5.1 Violation of the approved areas of each unit
1.5.1.1 10% area violation : 25% of the base rate for the violated area.
1.5.1.2 More than 10% but upto 20% area violation : 50% of the base rate for the violated area above 10%.
1.6 Projections :
1.6.1 Extra projected distance of chajja :
1.6.1.1 25 % of the approved distance : 25% of the base rate
1.6.1.2 More than 25 % and upto 50% of the approved distance : 50% of the base rate
1.6.2 Extra Projected Distance for floor
Upto 33% of the approved distance : 50 % of the base rate